The multi-use bridge spanning I-285 between Suntrust Park and the Cobb Galleria has been a topic of note in recent months, with critics questioning its apparently low budget estimate and supporters lauding its connection to much needed parking.
Today during the Cobb Board of Commissioners’ meeting the Board will vote on whether to move ahead with the project, a vote which is expected to pass easily.  If all goes according to plan, bridge construction could be underway as early as next month.

The following Cobb Chairman Tim Lee’s most recent update on the state of the bridge project.
The multi-use bridge is an important public safety project for the Cumberland area. It will connect 2 major commercial centers and ensure the safety of tens of thousands of people who visit, live, work and play in this area every single day.
 
Since January there has been a tremendous amount of progress made on this project:
 
January 7, 2016: The Cumberland Community Improvement District (CCID) approved providing $5 million in funding toward the bridge.
 
January 26, 2016: The Cobb County Board of Commission unanimously approved the bridge design.
 
February 2, 2016: The Cobb-Marietta Coliseum and Exhibit Hall Authority approved the bridge design.
 
February 25, 2016: Advertisement for bids posted.
 
March 31, 2016: 3 bids received.
 
During Tuesday’s Board of Commissioners meeting, the Board will consider 4 separate agenda items that will move this critical public safety project forward.
1. A framework agreement with the CCID to move forward with funding.
2. An agreement to relocate utilities that need to be moved due to the construction of the bridge.
3. A contract with Northwest Express Roadbuilders for construction of the bridge.
4. A supplemental agreement for additional engineering and design services for the bridge.
 
Bridge Costs
Engineering & Design             $939,621
Utility Relocation                      $56, 530
Bridge Construction                $10,085,408
Right of Way                               TBD
 
Click here to view detailed funding statements as outlined in the agenda.
 
Next Steps
Continue to work on agreement with partners at the Cobb-Marietta Coliseum and Exhibit Hall Authority.
Continue to work on right of way acquisition with partners on both the Circle 75 and Galleria landing points.
Begin construction on the bridge. 
 
Click here for additional information on the Multi-Use Bridge.